The Public Works Department is currently completing important summer maintenance on the Township roads

Brushing

Starting July 12th brushing operations will be occurring along Pinery Road to increase roadway safety.

Culvert Replacements and Ditching

Starting Monday, July 19th Culvert replacement and ditching will be occurring along two roadways:

Code Drive - between Nolan's and Rosedale

Montague Boundary – between train tracks and Pinery Road

Asphalt Paving

Second Street and O'Malley Street will have paving completed by the end of July (weather dependant)

Micro Surfacing

The Miller Group will be completing Micro Surfacing activities throughout the Township beginning in early August.

Please watch for updates on the when the roads will be closed

By accepting you will be accessing a service provided by a third-party external to https://www.montaguetownship.ca/

Montague white logo

Township of Montague

6547 Roger Stevens Drive
P.O. Box 755
Smiths Falls, ON K7A 4W6

Phone: 613‑283‑7478
Email: admin@township.montague.on.ca

Hours of Operation:
Monday to Friday - 9:00 a.m. to 4:30 p.m.